6 August 2018

Building the foundation

Frans Rombouts of Consortium EMA: "The foundation block underneath the large core has now been completed. In it are all elevator shafts. The two large cranes are operational. We started making the formwork partitions for the so-called sliding case in order to cast concrete for the core of the building. The concrete casting process is expected to start in mid-August. This 'sliding process' continues 24 hours a day. As a result, the concrete core will be at heights after about 4 weeks.